Construction
May 23: The Parish Hall now has steel walls and is coming along quickly behind our school and ECC buildings. Please join us for any of the future scheduled Tours and Treats to get a first hand look at our construction!

April 24: Children from the school and ECC got the chance this week to leave their mark on our new buildings by signing beams that will be errected within the new PreK/Kinder wing of the school and the ECC expansion. While the beam will be covered up during construction, the 2012 classes at St. Rose of Lima community have left their indelible impression on our school. What a way to commemorate our growth!


April 23: The dirt and foundations that once only showed the perimeter of our buildings have become three dimentional as steal was erected. We can now truly see the shape of our future building.

March 17, 2012: Concrete footings were poured for the ECC and Pre-K wing. This is the first step in building support for the steel beams and foundations to come.



February 22, 2012: The permitting process with the city is complete. The concrete back section of the ECC parking lot has been torn up and the breezeway between the school and the church has been removed.

January 29, 2012: Safety fences have been put up in and around the main parking lot and Rose Garden, the ECC parking lot, and the Pre-K/Kinder playground and school field.

January 8, 2012: Our St. Rose statue, along with the rose bushes and several other plants from the Rose Garden have been relocated around campus to begin preparations for our New Parish Hall.